JDIP Rehabilitation Works - Belgrade Heights

 

Works on Belgrade Heights commenced on July 5, 2011 and was completed October 28, 2011.

 

This project involved the rehabilitation of 1.2km length of road and the application of 900 meter square of asphaltic concrete.

 

Scope of works included:

  • Construction of Kerb and Channels
  • Construction of Retaining Walls
  • Patching
  • Paving